|
WARRINGTON 2 Progress |
|
||||
| Monday
30th June 2008 - new update on Warrington No2.
Work is progressing well on the Enclosed Dash at A. end. New Ash transom window and waist rails are being fitted. This type of work requires a lot of skill, time, and attention, due to the changing angle of each window at each stage. (Pics by Denis Butler) |
|||||
|---|---|---|---|---|---|
![]() |
![]() |
||||
![]() |
![]() |
||||
| Thursday 29th May 2008 - yet another update! | |||||
![]() |
Latest
pic of Warrington 2 showing the first transom window and waist rail.
(Photo
Mike Mercer) |
||||
|
Monday 28th April 2008 - an update. The
new stairs have been removed temporarily |
![]() |
||||
![]() |
![]() |
||||
![]() |
|||||
| Saturday 15th December 2007 - Work proceeding at a steady pace (Pics by Denis Butler). | |||||
|
Undercoats for Citrus and Crimson Lake paint being tested. |
General view of interior. |
||||
|
Both sides of the lower saloon outer panelling now completed. |
Bulkhead doors and mechanism being fitted. |
||||
|
Ceiling panels in place and awaiting new light fittings. |
Longitudinal seating prior to varnishing. |
||||
|
Second longitudinal seat frame being constructed. |
Staicases in place at both ends, Awaiting construction of enclosed dash. |
||||
| Thursday 9th August 2007 - Tonights working party continues to refurbish Warrington No2 (pics by Jonathon Howard) | |||||
![]() |
![]() |
||||
![]() |
![]() |
||||
| Thursday 2nd August 2007 - Some new pictures of Warrington No2 by Denis Butler. | |||||
![]() |
![]() |
||||
| (above
left) New paneling being fitted on side 2.
|
![]() |
||||
|
Wednesday 4th July 2007 - latest work in progress pictures by Denis Butler. GREAT PROGRESS DURING THE MONTH OF JUNE. Electrical wiring is almost complete. Outer panelling on one side of the lower deck is completed and the new stairs well under way. The boys have done well. |
|||||
|
(below) side view of new stairs 14-06-2007 |
Stairs in place 29-06-2007 (below) |
||||
![]() |
![]() |
||||
| Wednesday 13th June 2007 - latest work in progress pictures by Denis Butler. | |||||
| Mike
Mercer and Harry Bryant checking out the dimensions for the new stairs. |
Internal work in progress. | ||||
![]() |
![]() |
||||
| Switch panel ready for fitting. | Bob Sanders is about to fit the new fuse box for the interior lighting. | ||||
![]() |
![]() |
||||
![]() |
|||||
|
Monday 9 th April 2007 - work in progress pictures this time by Denis Butler. Tony McGreavey in
the orange overalls is about to climb all over the upper deck of No2 |
|||||
![]() |
![]() |
||||
![]() |
(Above) Rob Jones pointing towards the boxes of refurbished interior parts for the lower saloon.
(Left) Part of the original wiring that has been kept for display. This would not meet modern day regulations.
(Below) Exterior paneling will be starting soon. |
||||
![]() |
![]() |
||||
| Friday 6th April 2007 - work in progress pictures by Mike Mercer, and a 1907 postcard of a Warrington tram on the New Bridge from Denis Butler. | |||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
|||||
| The first new sole bar was fitted to Warrington No2 on Thursday the 8th February 2007. (photo by M.Mercer) | |||||
![]() |
![]() |
||||
| The
first progress report of the year - Friday 26th January 2007 Warrington No 2 platforms have been fitted and this is a good start to the New Year. Some more photos taken by Mike Mercer: |
|||||
![]() |
![]() |
||||
| The restoration
on Warrington No2 has started Big Time. The new platform bearers have been
fitted to one end. As soon as they are fitted on both ends the body can
be lifted off the A frames. This means that the steel angle can be removed
and the body frame can be inspected and replaced where required. Here are
the latest photos taken by Mike Mercer. |
|||||
|
![]() |
||||
Warrington
Tram Ticket 1930's (Denis Butler Collection)![]() |
|||||
|
Sunday 10th September 2006 The platform ends
have been removed so that work can be carried out on the rest of the body
frame. (Photo Mike Mercer) |
|||||
![]() |
|||||
|
A few pictures from Denis Butler showing the work being carried out. |
|||||
![]() |
![]() |
||||
| Steel under frame to be removed. | Coach Bolt heads removed. | ||||
![]() |
![]() |
||||
| Mike & Co.Two MTPS members standing on the platform of No2. Can you spot which one is Mike. |
When MTPS member Harry Bryant starts work the sparks start flying. |
||||
|
|
|||||
|
Friday 16th June 2006 The lads at Taylor
Street moved Warrington No2 out of the yard and in to the tramshed on
Thursday night the 8th June 06. (pictures from Jonathon Howard and Rob Jones) |
|||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
|||||
| The Thursday night working party. | |||||
![]() |
|||||
|
Saturday 20th May 2006 A few pictures from Jonathon Howard which show the results of rubbing down some orginal panels to reveal the coat of arms and the fleet number, others show work on the internal bulkheads & windows plus the kicker boards. |
|||||
![]() |
![]() |
||||
![]() |
![]() |
||||
![]() |
![]() |
||||
|
Sunday 30th April
2006 Gradually the 100 year old seat backs are being brought back to life. King of the Seat Backs - Rob Jones at work. (right) (below) Work team
from left to right. Terry Martin catches everyone`s attention using a
machine that makes square holes! Yes it is the mortise machine cutting
new timber for the damaged quarter lights. |
![]() |
||||
![]() |
|||||
|
Tuesday 4th April 2006 More pictures from
the Warrington No2 workshop team. Jonathan Howard
was busy last Saturday, working on Warrington No 2, and has supplied us
with more pictures of the continuing restoration. "What they show
is my attempt at speeding up the vast amount of paint stripping we have
got to do! I took all the lower saloon doors and the internal bulkhead
from B end outside, covered them in paint stripper, left them for 20 minutes
or so then blasted all the muck and paint off with my pressure washer.
Must say I think they turned out very well!" |
|||||
|
|
![]() |
||||
![]() |
![]() |
||||
| Above are the A end doors.... | ...and those from B end, after being hosed down. | ||||
![]() |
![]() |
||||
![]() |
|||||
|
Tuesday 28th March 2006 Latest pictures from the Warrington No2 workshop team. |
|||||
|
Junior Team, Dale and Rob working on seat frames. (above) |
![]() |
||||
|
|
(Above) Jonathan at work. Terry and Dale
working under the watchful eye of Peter (all pics by D.Butler)
|
||||
|
Wednesday 8th March 2006 Restoring the interior woodwork continues. |
|||||
|
Above and right) Lower saloon mouldings refurbished. (all pics by J.Howard & D.Butler) |
![]() |
||||
![]() |
(Left) Removing
many layers of paint form the lower saloon ceiling after more than 70
years.
(Below) Finding
an ornate centre piece and corners. |
||||
|
![]() |
||||
![]() |
![]() |
||||
| (Below) Brass window catches before and after cleaning and polishing. | |||||
![]() |
![]() |
||||
![]() |
More interior moulding
being restored.
|
||||
| Saturday 28th January 2006 | |||||
![]() |
|||||
|
Work continues on restoring the interior woodwork. (pic by D.Butler) |
![]() |
||||
| Latest report, Tuesday 29th November 2005 | |||||
|
|
![]() |
||||
| MTPS
member Jonathon Howard restoring the original mouldings from the lower saloon
ceiling. |
After nearly seventy years the lower saloon mouldings are seeing the light of day. | ||||
![]() |
![]() |
||||
| Upper
deck seats are being de- rusted, primed and undercoated in preparation for
their Maroon top coat. |
|||||
![]() |
![]() |
||||
| Interior fittings have had many coats of paint removed and await finishing. | |||||
| Sunday 13th February 2005 (All pics by D.Butler) | |||||
|
|
![]() |
||||
| An assortment of vital components have been obtained for Warrington No2 including , Controllers, Air Tanks, Sand Hoppers, etc. |
At last, after
70 years, a truck for Warrington No2. |
||||
|
How Warrington No2 should look when finished. |
|||||
![]() |
|||||
|
Warrington No.2 transported from St Helens to Woodside On Saturday 24th July 2004, Warrington No.2 was safely delivered to Taylor Street depot and now awaits restoration by MTPS members.
(pic by D.Butler)
|
|||||
![]() |
![]() |
||||
| Warrington
No.2 being prepared for lifting at St Helens Transport Museum. (pic by D.Butler) |
THE VERY LAST TRAM EVER TO LEAVE ST HELENS TRAM DEPOT WAS WARRINGTON No.2 on Saturday 24th July 2004. Destination Taylor Street Birkenhead for future restoration. (pic by D.Butler) | ||||
![]() |
![]() |
||||
| Arrival at Taylor Street Saturday 24th July 2004. | Preparing to hoist Warrington No.2 off the wagon. | ||||
|
Up she goes... |
![]() |
||||
|
...and down onto
a trailer to be stowed away between the containers. |
![]() |
||||
![]() |
Warrington no.8, from the same batch as no.2. Originally open-topped, they were later given top covers. (left) (D.Butler collection) | ||||
|
|
|
||||